Court Denies Tarrytown’s Challenge to Lighthouse Landing Project on General Motors’ Property

On September 12, 2012, acting Supreme Court Justice James W. Hubert issued a decision denying the Village of Tarrytown’s petition challenging the Village of Sleepy Hollow’s approval of the mixed use 96-acre Lighthouse Landing Project on General Motors’ Property on Beekman Avenue and River Street in the Village of Sleepy Hollow.  A copy of the Court’s decision can be found here.

The primary basis for the appeal was Tarrytown’s belief that the proposed project would have a significant adverse impact on traffic and parking in Tarrytown.  Specifically, Tarrytown claimed that increased traffic caused by the project, coupled with the reduction of parking on Route 9 (a.k.a. Broadway) in Tarrytown would have a significant adverse impact on the residents and business owners in Tarrytown.  Although Tarrytown claimed that Sleepy Hollow did not take a “hard look” at the traffic and parking impacts, as required by the State Environmental Quality Review Act (SEQRA), the Court examined the zoning record, cited to a litany of consultants’ reports (including a traffic report that looked at a myriad of intersections in Tarrytown) and public hearings, finding that Sleepy Hollow did in fact take the requisite “hard look” under SEQRA.  The Court also noted in its decision that Sleepy Hollow imposed certain restrictions on the project in order to mitigate some of the environmental impacts, including a reduction in the number of dwellings and commercial space and shuttle buses to the train station.

The Court also disagreed with Tarrytown’s argument that Sleepy Hollow did not adequately reconcile its SEQRA finding statement with Tarrytown’s SEQRA findings statement with respect to traffic and parking.  The Court found that Sleepy Hollow, as lead agency under SEQRA could make findings that differed from Tarrytown’s (an involved agency) and that these differences need not be reconciled.

As a procedural matter, the court also found that a supplemental environmental impact statement was not necessitated by certain changes in the project.

This court decision represents a significant victory for Sleepy Hollow, which is looking to clean up the old General Motors property (a brownfields site), promote economic development, and regain access to its waterfront.

Please do not hesitate to call our office at 914-338-8050 if you have any questions regarding the State Environmental Quality Review Act or land use/zoning in general.

Leave a Reply

Your email address will not be published. Required fields are marked *

Contact Us

Give us a call or fill in the form below and we will contact you. We endeavor to answer all inquiries within 24 hours on business days.